Project Start Date: Mon 11/9/98
Project Finish Date: Tue 12/1/98
Resources and Assignments | Start | Finish | Work |
---|---|---|---|
Mei Fun Wong | Mon 10/12/98 | Tue 12/1/98 | 184 hrs |
Testing | Tue 11/24/98 | Wed 11/25/98 | 16 hrs |
Demonstrate and Deliver new System to Daycare Center | Thu 11/26/98 | Thu 11/26/98 | 8 hrs |
Make appointment with Dr. Hines | Tue 12/1/98 | Tue 12/1/98 | 8 hrs |
Compile project 1 | Thu 10/15/98 | Sat 10/17/98 | 16 hrs |
Review Scope of System | Sun 11/1/98 | Thu 11/12/98 | 72 hrs |
Parents Database Forms Coding | Fri 11/13/98 | Thu 11/19/98 | 40 hrs |
Proposed System | Mon 10/12/98 | Wed 10/14/98 | 24 hrs |
Meng Yi Yee | Mon 10/12/98 | Tue 12/1/98 | 176 hrs |
Integrating into an Application Software | Fri 11/20/98 | Mon 11/23/98 | 24 hrs |
Demonstrate and Deliver new System to Daycare Center | Thu 11/26/98 | Thu 11/26/98 | 8 hrs |
Make appointment with Dr. Hines | Tue 12/1/98 | Tue 12/1/98 | 8 hrs |
Review Architectural Design | Sun 11/1/98 | Thu 11/12/98 | 72 hrs |
Children Database Forms Coding | Fri 11/13/98 | Thu 11/19/98 | 40 hrs |
Non-funtional Requirements | Mon 10/12/98 | Wed 10/14/98 | 24 hrs |
Marlainna Glenn | Mon 10/12/98 | Tue 12/1/98 | 168 hrs |
Testing | Tue 11/24/98 | Wed 11/25/98 | 16 hrs |
Demonstrate and Deliver new System to Daycare Center | Thu 11/26/98 | Thu 11/26/98 | 8 hrs |
Make appointment with Dr. Hines | Tue 12/1/98 | Tue 12/1/98 | 8 hrs |
Problem System | Mon 10/12/98 | Mon 10/12/98 | 8 hrs |
Current System | Tue 10/13/98 | Wed 10/14/98 | 16 hrs |
Review Data Design | Sun 11/1/98 | Thu 11/12/98 | 72 hrs |
Accounts and Forms Coding | Fri 11/13/98 | Thu 11/19/98 | 40 hrs |